New Library/Community Center progress August 2019 update

Work on programming to determine square footage, budget and site planning. The Architects worked with the Building Committee throughout the month analyzing each of 14 areas in the library. The winnowing process to achieve a balance between needs and wants in order to determine the square footage footprint is still in progress.  The Library Board hired attorney Kim Hurtado of Hurtado Zimmerman SC for construction lawyer. An RFP for Owner’s Representation resulted in three responses. The Board hired Tom Baade and Kory Krieser of Integris Risk Management for Owners representative. An ALTA Survey of the John Street property was completed. The Building Committee toured maker spaces at Parkview school and the Mayville High school and continues to analyze how to best use a Makerspace for the community.